How to Change SiteWorx Billing Day

Prerequisites

Last Updated for InterWorx-CP version 2.1.0

An existing SiteWorx account.

Purpose

The purpose of this is to detail how to change the billing day for a SiteWorx account using NodeWorx.

Procedure - Change SiteWorx Billing Day

  1. Click on the SiteWorx menu if it is not already expanded.
  2. Click on the ♦    Accounts item.
  3. You should now be looking at the SiteWorx Account Management controls in the main content area.
  4. Click the [ Edit ] link next to the SiteWorx account you wish to edit.
  5. Locate the Base Information section.
  6. Select the new billing day from the drop-down list labeled Billing Day.
  7. Click the Save button at the bottom of the screen.
  8. You will see the following message: » SiteWorx account edited successfully.

Billing Day Examples

Change the Billing Day to a Day After the Current Billing Day

If the day that you choose for the billing day is after the current billing day, the billing period will end on the day before the billing day at 11:59 p.m. and the new billing period will start at 12:00 a.m. on the billing day. The start of the billing period is not changed, therefore changing the billing day to a day later than the current one will result in an elongated billing period.

Example - Billing Day Set to 14 (the 14th of every month)

Billing DayPeriod StartPeriod End
14 Sep. 14th, 12:00 a.m. Oct. 13th, 11:59 p.m.

Now, if you change your billing day to 22, current billing period will adjust as follows:

Billing DayPeriod StartPeriod End
22 Sep. 14th, 12:00 a.m. Oct. 21st, 11:59 p.m.

The following billing period will be back to the normal set of time and run as follows:

Billing DayPeriod StartPeriod End
22 Oct. 22nd, 12:00 a.m. Nov. 21st, 11:59 p.m.

This is an example of an elongated billing period. The bandwidth counters will not reset to 0 until the new period begins at 12:00 a.m. October 22nd.

Change the Billing Day to a Day Before the Current Billing Day

If the day that you choose for the billing day is before the current billing day, the billing period will end on the day before the billing day at 11:59 p.m. and the new billing period will start at 12:00 a.m. on the billing day. The start of the billing period is not changed, therefore changing the billing day to an earlier day than the current one will result in a shortened billing period.

Example - Billing Day Set to 14 (the 14th of every month)

Billing DayPeriod StartPeriod End
14 Sep. 14th, 12:00 a.m. Oct. 13th, 11:59 p.m.

Now, if you change your billing day to 7, current billing period will adjust as follows:

Billing DayPeriod StartPeriod End
7 Sep. 14th, 12:00 a.m. Oct. 6th, 11:59 p.m.

The following billing period will be back to the normal set of time and run as follows:

Billing DayPeriod StartPeriod End
7 Oct. 7th, 12:00 a.m. Nov. 6th, 11:59 p.m.

This is an example of a shortened billing period. The bandwidth counters will not reset to 0 until the new period begins at 12:00 a.m. October 7th.

 In either case, the start of the current billing period never changes.